Commercial solar EPC and plant energy assessment

Assess solar generation against the site's electricity demand, available area, grid interface and operating constraints before selecting capacity.

Discuss this requirement
Illustrative process view

The engineering context

What the assignment needs to resolve

A CBG plant's electrical load often continues outside solar generation hours. Solar sizing should therefore begin with an hourly load profile and the site's grid arrangement, not only with annual electricity consumption. Installed kWp and reliably displaced grid energy are different quantities.

For a new ground-mounted installation, the assessment covers usable land, shading, access, drainage, soil conditions, cable routes and the connection point. A production estimate is then compared with daytime self-consumption, permitted export and the applicable tariff structure. Storage or backup, where required, is a separate design and economic decision.

Inputs for a useful solar assessment

InputWhat to examineEffect on the proposal
Load profileOperating equipment, shift pattern and daytime minimum loadSelf-consumption and potential export
Land and layoutUsable area, shading, access and future plant expansionPractical DC capacity and arrangement
Electrical interfaceConnection voltage, sanctioned demand and protection requirementsEvacuation scope and approval dependencies
Energy modelWeather data, orientation, losses and degradation assumptionsExpected annual and monthly generation
Commercial basisTariff, export treatment, maintenance and replacement assumptionsSavings and sensitivity to operating changes

Altpreneur scope

How we approach the work

01

Site and load assessment

Review interval or monthly consumption, available ground or roof area, shading, access and the electrical connection. For new CBG plants, use the planned load profile and expected operating schedule.

02

Technical design

Define the array, inverter, cable and protection concept. Coordinate structural or ground-support requirements, drainage, earthing and safe maintenance access.

03

Commercial evaluation

Compare self-consumption, export assumptions, tariffs and financing sensitivities. Confirm the applicable state and utility pathway for the proposed installation.

04

Execution and handover

Coordinate procurement, installation, commissioning documentation and operating handover within the agreed project scope.

Decisions worth getting right

Use the right savings boundary

Electricity generated, consumed on site, exported and curtailed should appear separately. Applying the retail tariff to every generated unit can overstate savings.

Allow for plant expansion

A solar layout should not block future process equipment, roads, fire access or maintenance movement. Review the long-term site plan before fixing the array.

Keep grid and backup functions explicit

A conventional grid-connected solar system does not automatically provide power during an outage. Any islanding or backup requirement must be designed and approved specifically.

Assignment outputs

What you receive

  • Site and demand assessment
  • Indicative capacity and generation model
  • Electrical and layout concept
  • Scope, budget and execution programme
  • Commissioning and maintenance documentation

To begin

Useful starting information

  • Electricity bills and demand profile
  • Site location and available area
  • Grid-connection details and operating hours

Scope and responsibility

Grid approvals, export permissions and tariffs are location-specific. Conventional grid-connected solar alone does not maintain supply during a grid outage; backup requires a separately engineered arrangement.

Common questions

Can solar supply all CBG plant electricity?

Daytime output and plant demand must be compared hour by hour. Night operation, starting loads and outages require grid or appropriately designed backup support.

Can the study cover ground-mounted solar before construction?

Yes. Available ground, grading, shading, irradiation, grid distance and the plant's other land requirements should be assessed together.

Evidence & further reading

Source material

  1. US Department of Energy: Solar potential and PVWatts estimation
  2. US EPA AgSTAR: Project Development Handbook

Technical references inform the discussion. Final design, operating limits and policy eligibility depend on the project and applicable current documents.